Latest Updates — Wales
UPDATED
🏴󠁧󠁢󠁷󠁬󠁳󠁿 Wales Transport for Wales’ first new Class 197e trains entered passenger service on the Cambrian Coast Line (TfW, 22 Oct 2026). The £1.5bn Core Valley Lines transformation won the ICE Sir John Armitt Prize at the British Construction & Infrastructure Awards (The National Wales, 21 Oct 2026).
Northern Ireland — DrumcreeDrumcree stand-off: the parade was banned on 9 Oct 2026 after 13 days. Justice Minister Naomi Long told the Assembly the policing cost is now estimated at £5.5m (19 Oct 2026). See the NI dashboard.→ Northern Ireland — A5 ruling, 6 Oct 2026A5 Western Transport Corridor: the Court of Appeal in Belfast today allowed DfI’s appeal on all grounds, lifting the legal block on the first phase (ITV News; Irish Times; Belfast Live, 6 Oct 2026). The Alternative A5 Alliance can still seek permission to appeal to the UK Supreme Court; no application has been reported. Cost of delay: had it gone ahead as planned in 2012 (completion 2018), the approved business case was £799m (£975m at 2017 prices); it is now £2.1bn (DfI, Oct 2024) — roughly £1.1bn–£1.3bn more to be borne, plus £192.5m already spent with no road built (NIAO 2019; DfI, Sep 2026). For the families of the more than 50 people killed on the A5 since 2006 (ITV News; BBC), it is a day when their prayers were in some way answered — CPD hopes no further lives are lost while the scheme moves forward, with Climate Change Act compliance remaining an important factor. No construction start date yet.→
In memory of the 58 people who have lost their lives on the A5 since 2007 (Donegal News, 3 Nov 2026) — A5 Enough is Enough
Construction costs — 10-year check, 2016 to 2026Has building nearly doubled in cost in ten years? In Ireland, almost: commercial tender prices rose 83% from the first half of 2016 to the first half of 2026 (SCSI Tender Price Index, Aug 2026). In Great Britain the rise is closer to half than double: prices paid for new construction work rose 47% from June 2016 to June 2026 — housing 55%, infrastructure 44%, public buildings 41% (ONS construction output price indices, Aug 2026). Building materials rose faster, 68% from the 2016 average to August 2026 (DBT, provisional), against 42% for general prices over the same ten years (ONS CPI). No official Northern Ireland-only price index exists: NISRA price-adjusts NI construction output using these ONS indices because “regional OPIs are not available” (NISRA construction methodology report, Dec 2025). Construction has outpaced general inflation, so every year a scheme drifts it is re-priced in a dearer market.Non-official comparison — not an official statisticRider Levett Bucknall, a private consultancy, forecasts Northern Ireland tender prices to rise 3% in 2026 and 3.25% a year in 2027, 2028 and 2029 — about 13% over the four years if compounded (CPD calculation). RLB names labour as “the most significant driver of construction inflation” in NI. This is a commercial forecast, not a measured 10-year change (RLB Construction Market Intelligence, Northern Ireland, Q3 2026).
🌍All jurisdictionsOpen the British Isles & Australia hub for updates across all seven jurisdictions, the separate per-currency overrun clocks and the reconciliation panel.→
ExtendIQ SiteIQ NI
LATEST
Delays13 of 40 schemes in Significant Delay · 7 Minor Delay · 5 Cancelled · 9 Not Started · 5 On Track · 1 Paused● Cost Clock£42.85/sec — Wales overrun clock running since 30 Apr 2026 — base overrun £9.582bn● Cancelled5 schemes Cancelled including M4 Relief Road — abandoned after public inquiry — significant sunk cost● New SchemesLlanwern Station, Gabalfa Interchange, Eryri Transport Hub and Swansea Arena added — now 40 schemes tracked● RailSouth Wales Metro: multiple packages in Minor and Significant Delay — valley line electrification ongoing● ScoreCPD scores live-calculated from all 40 scheme data points — base overrun £1.271bn● Delays13 of 40 schemes in Significant Delay · 7 Minor Delay · 5 Cancelled · 9 Not Started · 5 On Track · 1 Paused● Cost Clock£42.85/sec — Wales overrun clock running since 30 Apr 2026 — base overrun £9.582bn● Cancelled5 schemes Cancelled including M4 Relief Road — abandoned after public inquiry — significant sunk cost● New SchemesLlanwern Station, Gabalfa Interchange, Eryri Transport Hub and Swansea Arena added — now 40 schemes tracked● RailSouth Wales Metro: multiple packages in Minor and Significant Delay — valley line electrification ongoing● ScoreCPD scores live-calculated from all 40 scheme data points — base overrun £1.271bn●
Total Cost Overrun — All 40 Schemes
—
% above announced cost across all schemes
Total Portfolio — Current Estimated Cost
—
Across all 40 tracked Wales schemes
CPD Index — Wales Lower score = worse delivery performance (0 = total failure, 100 = perfect)
CPD-C | Cost Performance
0
/ 100
🟠 Poor
CPD-D | Delivery Performance
0
/ 100
🟡 Concern
CPD Combined Index
0
/ 100
🟠 Poor
Portfolio Overview

Programme Status Breakdown

Delay Distribution (Weeks)

Announced vs. Current Cost — All Schemes (£m)

Cost Escalation Forecast to 2032 — Active Schemes

Key Facts

A465 — 23 Years, £1.5bn Over Budget

The Heads of the Valleys dualling began in 2002 and completed May 2025 — 23 years later. The total programme cost reached approximately £2bn against an original estimate of £500m. Sections 5 & 6 alone carry a 30-year MIM payment commitment of £1.4bn. Audit Wales confirmed Section 2 came in 46% over its 2014 construction start estimate.

Velindre Cancer Centre — Active Construction, Spring 2027

The new Velindre Cancer Centre in Cardiff is actively under construction (Jun 2026): the tower crane was dismantled following completion of the structural frame, and extended working hours are approved through July 2026 to maintain programme. Opening remains spring 2027. While 25-year lifecycle costs (Audit Wales, Feb 2026) have risen to £1.65bn — nearly three times the 2021 Outline Business Case — the contracted construction cost of £321m is on programme. Status upgraded to Minor Delay.

NHS Wales Backlog Hits £917m

High and significant risk maintenance backlog across 210 NHS Wales buildings reached £917m in 2024-25 — a 71% increase in four years. Over £616m relates to critical issues at 12 of Wales' 13 main hospitals. Ysbyty Gwynedd (£110.5m) and University Hospital of Wales (£106.8m) top the list. Welsh Labour's election manifesto proposed a £4bn "Hospitals of the Future" fund.

M4 Relief Road — £135.7m Written Off

The proposed M4 Newport bypass was cancelled in June 2019 after 28 years of planning. A total of £135.7m in public money was written off by 2021, including £44m on a public inquiry. By 2026, M4 congestion at Newport remained unresolved and the scheme re-emerged as a Senedd election issue — meaning even the sunk costs failed to deliver a lasting policy resolution.

South Wales Metro — £566m Over, 3 Years Late

The Core Valley Lines electrification completed in March 2026, three years behind the original 2023 target. Cost rose from £734m (2016) to approximately £1.3bn — a 77% increase — with TfW CEO James Price telling the Senedd that a further £150m had been added in early 2026. The full benefit timetable will not be operational until 2026 signal works at Cardiff Queen Street complete.

Scheme Register 40 schemes tracked · click row for details
Sort:
Scheme Status Announced Current Est. Variance Delay ETI Stranded Detail

Methodology & Sources

CPD Index (0–100): CPD-C (Cost Performance) measures the proportion of schemes delivered at or near announced cost, with a severity penalty for overruns greater than 25%. CPD-D (Delivery Performance) measures the proportion of schemes free from significant delay, with a minor penalty for smaller slippages. The combined CPD score applies a 60/40 weighting — 60% CPD-D (Delivery) and 40% CPD-C (Cost), reflecting the judgement that delivery failure imposes compounding societal and economic costs beyond the overrun figure alone. A score of 100 indicates a perfect delivery record; 0 indicates complete systemic failure.

Wales CPD scores: CPD-C = 45/100 (Poor 🟠): 18 of 40 schemes over budget; 7 with severe overruns (>25%) applying a 7-point penalty on the base 50 raw score. CPD-D = 69/100 (Concern 🟡): 6 schemes with significant delays (A465, S. Wales Metro, Velindre, Rolling Stock, NHS Backlog, Afan Valley) with a minor penalty of 1 point for 2 minor delay schemes. CPD Combined = 56/100 (Poor 🟠).

Clock: The live clock is computed from the scheme table on this page rather than from a stored total. It starts from the accumulated cost overrun on every scheme still live — any status other than Completed, Cancelled or Paused, with announced cost treated as zero where no published baseline exists — and then accrues construction inflation of 3.8% per annum (blended BCIS) on the live estimated portfolio from base epoch 30 April 2026. Completed, paused and cancelled schemes are excluded from the accrual. Both inputs are reproducible from the scheme table below, and the reconciliation panel shows the totals they derive from. Re-based 22 September 2026: the clock previously ran from a hand-selected subset of schemes that no longer reconciled with the published portfolio totals on this page.

Cost data: Announced costs are taken from original Welsh Government press releases, Senedd written statements, and Audit Wales reports. Current estimated costs are drawn from Audit Wales publications, Transport for Wales Senedd committee evidence, BBC Wales, WalesOnline, and gov.wales written statements.

Delay data: Weeks of delay calculated from original target completion date versus revised target or today's date where no revised target exists. Where no completion date was ever formally set, delay is classified as TBC.

Currency & inflation: All costs in £ GBP. Cost projections use BCIS blended rates: civil engineering 4.4% p.a., buildings 3.2% p.a.

Primary sources: Audit Wales (audit.wales) · Welsh Government (gov.wales) · Transport for Wales (tfw.wales) · BBC Wales · WalesOnline · Senedd committee reports

ETI — recognised by infrastructure funders and development economists: The ETI framework mirrors the approach used by infrastructure funders, bond markets, and recognised development economists when assessing the productive value of public capital expenditure. Its components draw on HM Treasury Green Book benefit-cost ratio methodology, deprivation weighting consistent with Levelling Up Fund criteria, and network effect analysis aligned with WebTAG multi-modal appraisal guidance — the same analytical frameworks referenced by the Infrastructure and Projects Authority, development finance institutions, and institutional investors when evaluating public infrastructure programmes.

Disclaimer: This tracker is an independent professional accountability tool prepared by QUINTIN QS. It does not replicate, replace, or compete with any official government appraisal process. ETI scores and Stranded Value figures are derived from publicly available benchmark data and established appraisal frameworks — they are not the output of scheme-specific transport models such as TUBA or WebTAG-compliant multi-modal assessments. BCR inputs are drawn from published or analogous benchmarks, not bespoke modelling. Deprivation weighting is adapted from Levelling Up Fund criteria and is indicative in jurisdictions that use different deprivation indices. Delivery certainty scores reflect professional judgement applied consistently across all schemes. The methodology is fully disclosed, reproducible, and grounded in HM Treasury Green Book principles as updated in 2026 — but it carries the status of an independent analytical indicator, not a statutory appraisal. All figures are drawn from publicly available sources and are correct as of the date shown. If any government department holds more accurate data for a specific scheme, QUINTIN QS will update immediately upon notification. 🍓 If you believe any figure or fact shown here is incorrect, please write to mail@kevinbarryqs.com with the relevant scheme name, the correct figure, and a source reference — we will review and correct immediately if the evidence supports it. We are, after all, still human.

CPD Index — cost cap: The cost overrun % contribution to CPD-C is capped at 50 points — schemes with overruns above 100% score the maximum on this component. This prevents extreme outliers (e.g. schemes with 200%+ overruns) from distorting the index beyond its intended range.

CPD — about this acronym: CPD stands for Continued Prolonged Delays — a deliberate reference to Northern Ireland's Central Procurement Directorate, rebranded as Construction, Procurement, Delivery — the NI Executive body whose mandate is to ensure public infrastructure is built on time and on budget. The name is intentional.

Fewer promises.  Properly prepared projects.  Honest cost ranges.  Protected funding.  Named accountability. Build, reset or stop — never leave a project drifting indefinitely.